2007

Termin realizacji Opis
2007 - 2008 Pątnów II Power Plant – gypsum dewatering and storage system – fire detection installation for telecommunication, IT and access control, for RAFAKO S.A. (consortium with ABB)
2007 - 2008 Pątnów II Power Plant – gypsum dewatering and storage system – delivery of material and complete assembly of automation, for RAFAKO S.A. (consortium with ABB)
2007 - 2008 Pątnów Power Plant - flue gas desulphurization installation of units 1, 2, 3, 4 200 MW – delivery of materials and complete assembly of automation, for ABB Polska
2007 - 2008 Pątnów Power Plant – flue gas desulphurization installation of units 1, 2, 3, 4 200 MW – complex execution of fire detection installation for telecommunication IT and access control, for ABB Polska
2007 - 2008 Pątnów II Power Plant – execution of pipeline heating system, for IZOKOR Płock
2007 - 2008 Tauron EnergiaPro – 110/20kV “Jawor” power station – execution of automatic reactive power compensation – design and construction of 2 capacitor banks, for Tauron EnergiaPro
2007 - 2008 Tauron EnergiaPro – 110/20kV “Północna” power station – execution of automatic reactive power compensation – design and construction of 2 capacitor banks, for Tauron EnergiaPro
2007 - 2008 Tauron EnergiaPro – 110/20 kV “R-Boguszów” Power station in Boguszów Gorce – upgrade of 110 kV switching substation, for EnergiaPro
2007 DALKIA “EC Karolin” – automation of 13UP65 turbine regulation system on BC-50 unit for EMERSON PMPWS
2007 Zduńska Wola S.A. Heat and Power Plant – reconstruction of 15kV switching substation cells, for Zduńska Wola HPP
2007 Pątnów II Power Plant – delivery and assembly of electrical devices and automation for light oil installation, for CONTROL PROCESS
2007 Pątnów Power Plant – execution of electrical and lighting installations on chimneys, for KARRENA
2007 - 2009 Adamów Power Plant – fire detection installation on power plant objects, for ZE PAK S.A.
2007 – 2008 Upgrade of monitoring system in Pątnów Power Plant, for ZE PAK S.A.
2007 - 2009 Pątnów Power Plant – fire detection installation on power plant objects, for ZE PAK S.A.
2007 - 2008 Unit 4 in Adamów Power Plant – complex upgrade of automation system, for ZE PAK S.A.
2007 Pątnów II Power Plant Unit A 460 MW – complex execution of automation of transfer tower and limestone dust storage on Flue Gas Desulphurization Installation, for SIEMENS Sp. z o.o.